Client’s needs

This chemical company had a scheduled shutdown of their decarbonisation plant for an inspection in March 2016. The client had to produce decarbonated quality water to feed their processes for demineralisation, softeners and TAR.

The initial contract was for 2 weeks but due to a delay on site the rental period was extended week per week.

Our solution

Mobile Water Services supplied worked with the client to meet their maintenance project timescales and keep their water supply going to avoid any disruptions to productions. The following technology was supplied:

  • 3 MOFI 3×60 + 3 MORO 4X25 – 250 m³/h

Benefits

  • Reliable and cost effective solution for a planned project